• Compilation of master programme and progress monitoring of the M6 Bromford Viaduct repair work contract, enabling the project to achieve its completion on schedule.

• Compilation of master programme and progress monitoring of the Tame Viaduct on the A38M in Birmingham, enabling the project to achieve its completion ahead of schedule.

• Analysing of progress and identifying specific areas for improvement on a £300M framework contract with Metronet.

• Demonstration of entitlement to recover losses on a contract to supply Rolling Stock for West Coast Mainline.

• Appointment as Planning Expert for Alstom at the International Court of Arbitration, Geneva, in a matter between Bombardier and Alstom for the supply of bodyshells for the Athens Metro. Based on Peter's Expert Report, the Court found in favour of Alstom.

• Production of a composite manufacturing programme for 5 separate rolling stock supply contracts to demonstrate disruption in a successful £12M claim against Railtrack.

• Producing recovery programme on a successful claim for £16M for Kier at Coulport.